Minnesota Department of Transportation

511 Travel Info

Hwy 53 – Eveleth Rock Ridge Transportation Improvements

St. Louis County

Traffic impacts

Construction will resume in May 2026. Final work includes constructing a drainage pond and paving trails. Some daytime lane and shoulder closures may be needed to complete work.

Summary of work

A rendering of the Hwy 53 intersection project.

Click image for full-size image

  • Remove and replace bridges at the interchange of Hwy 53 and Hwy 37
  • Safety improvements at intersections on Highway 53
    • Bourgin Road - geometric improvements
    • Progress Parkway - roundabout
    • Hat Trick Avenue - geometric improvements
  • Pavement resurfacing from Hwy 37 to Vermillion Drive
  • Improvements to sidewalks, trails, and intersection lighting

 

St. Louis County will also be completing work in this area. Visit the county's website for more information on their work.